Construction Updates

Posted on: July 26, 2024

[ARCHIVED] Secondary Water Project Update- July 26, 2024

About

Roosevelt City recently received a grant from the Utah Division of Water Resources for the installation of 11,500 feet of secondary water service line! The installation will happen over several phases this summer, starting with the Bonnie Drive neighborhood next Monday, July 1, 2024. 

Project details including project index sheets, and City codes relating to secondary water service connections and usage can be found by visiting the Secondary Water System Phase III Project page.  This page will be update as the project progress, and more information is available. 

Project Updates 

07/26/2024 Update – Roosevelt City Secondary Water Phase III Project

Johansen Construction continued on the secondary project, installing mainline on 350 North between 750 West and 1000 West, as well as on 300 North and 750 West. It is planned to complete the main line on 300 North and 950 West within the next couple of working days, and then crews will focus on installing services on those roadways as well. Thank you for the coordination that has occurred so far regarding meter placement, and we ask that those that have not placed the stakes for their meter location do so prior to crews arriving at your property. A reminder to move vehicles and trailers parked on the roadways between 7:00 A.M. and 5:30 P.M. in order to avoid interruptions to the project. Thank you for your cooperation and continued patience as the project continues.

07/19/2024 Update – Roosevelt City Secondary Water Phase III Project

Johansen Construction continued on the secondary project, installing mainline on 350 North between 750 West and 1000 West. Services were installed to multiple homes on that road this past week as well. It is anticipated that mainline installation will continue in the area, focusing on 950 West, 300 North, and 750 West followed by the installation of service lines and meters. Asphalt repair is included as part of the project; however, it will be completed at a later date. As construction continues, we ask that vehicles and trailers not be parked on the roadways between 7:00 A.M. and 5:30 P.M. in order to avoid interruptions to the project. Thank you for your cooperation and continued patience as the project continues.

07/12/2024 Update – Roosevelt City Secondary Water Phase III Project

Johansen Construction began the project on July 1, 2024, at 200 North and 1000 West. The main line has been installed on 1000 West as well as Bonnie Drive. Services, including service lines and meters, are being installed along that same stretch. The services should be completed soon and clean up and pressure testing are scheduled for the early part of the week of July 15. It is important to note that the trenches on 1000 West and Bonnie Drive will be backfilled with millings instead of repaired with asphalt. This is due to a road repair project that is scheduled for early 2025 to reconstruct both Bonnie Drive and 1000 West. Upon completion of the pressure testing, the crews will move to 350 North between 1000 West and 750 West where they will begin installing the main line. Thank you for your patience and understanding as the project continues.