Posted on: April 4, 2025

[ARCHIVED] Secondary Water Phase III Update April 4 2025

487928159_1008172731409746_1220883300509177268_n

04/04/2025 Update – Roosevelt City Secondary Water Phase III Project

The Secondary Water Project continued this week on 1875 South between State Street and 500 East. The main line and services installation have been completed. The contractor will return next Monday to repair a dilapidated valve in the intersection of 500 East and 2000 South. Depending on weather and the availability of asphalt, the road repair on 1875 South may take place next week as well. The contractor will also install an air release station on 100 South between 200 West and 100 West. We appreciate everyone’s patience and understanding as this project continues.